This Week / Home
Search Encyclopedia
Advanced Search
Home About Us Contact Us Education Bookstore Tourism Links Advanced Search
5645 HistoryLink.org essays now available      
Donate Subscribe

Shortcuts

Libraries
Cyberpedias Cyberpedias
Timeline Essays Timeline Essays
People's Histories People's Histories

Selected Collections
Cities & Towns Cities & Towns
County Thumbnails County Thumbnails
Biographies Biographies
Interactive Cybertours Interactive Cybertours
Slide Shows Slide Shows

Research Shortcuts

Map Searches
Alphabetical Search
Timeline Date Search
Topic Search
Links

Features

History Bytes
Book of the Fortnight
History Bookshelf
Past/Forward Calendar
Klondike Gold Rush Database
Duvall Newspaper Index
Wellington Scrapbook

More History

Washington FAQs
Washington Milestones
Honor Rolls
Columbia Basin
Everett
Olympia
Seattle
Spokane
Tacoma
Walla Walla
Roads & Rails

History Networking

Facebook Facebook
Twitter Twitter
   

Timeline Library

< Browse to Previous Essay | Browse to Next Essay >

Tacoma City Light joins Washington Public Power Supply System nuclear program in 1972.

HistoryLink.org Essay 5155 : Printer-Friendly Format

In 1972, Tacoma joins in construction of two nuclear power plants under construction by the Washington Public Power Supply System -- WPPSS -- in Hanford and at Satsop in Grays Harbor County. The move comes at a time when large-scale hydroelectric development had ended and utilities were turning to thermal sources -- coal, natural gas, and nuclear -- for energy. These reactors and two others will never be built because of massive cost overruns.

WPPSS was a governmental coalition organized in 1957 among publicly owned electrical utilities in Washington to share the costs of building new generating facilities. In the 1960s, planners told the utilities that the demand for electricity would double every 10 years. All the best hydroelectric sites had been exploited and environmental objections blocked any new projects. WPPSS started construction on two nuclear reactors, the cost to be paid by the sale of the power to consumers. In 1975, the system started two more plants -- 4 and 5 -- paired with the first two. Tacoma joined in these projects as well.

In addition to concerns about the safety and cost effectiveness of nuclear power, costs of the four plants grew. By 1979, the plants were 18 months behind schedule and the price had doubled due to mismanagement. In 1982, the WPPSS board suspended work on plants 4 and 5. Plants 1 and 3 were mothballed too, and finally cancelled. WPPSS defaulted on $2.25 billion in bonds. Tacoma paid $40.3 million to settle its share of the debacle. That was passed along to ratepayers in April 1983 as a 15 percent surcharge.

One nuclear power plant, WPPSS 2 – the Columbia Generating Station -- produced power. WPPSS later renamed itself Energy Northwest.

Sources:
Dick Malloy and John S. Ott, The Tacoma Public Utilities Story (Tacoma: Tacoma Public Utilities, 1993), 223, 260, 261, 274-277; David Wilma, "Washington Public Power Supply System," Historylink Metropedia Library (www.Historylink.org).

Licensing: This essay is licensed under a Creative Commons license that encourages reproduction with attribution. Credit should be given to both HistoryLink.org and to the author, and sources must be included with any reproduction. Click the icon for more info. Please note that this Creative Commons license applies to text only, and not to images. For more information regarding individual photos or images, please contact the source noted in the image credit.

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivs 3.0 Unported License

More information: < Browse to Previous Essay | Browse to Next Essay > | Search |
Related Topics: Infrastructure |

Major Support for HistoryLink.org Provided By: The State of Washington | Patsy Bullitt Collins | Paul G. Allen Family Foundation | Museum Of History & Industry | 4Culture (King County Lodging Tax Revenue) | City of Seattle | City of Bellevue | City of Tacoma | King County | The Peach Foundation | Microsoft Corporation, Other Public and Private Sponsors and Visitors Like You

This file made possible by:
Tacoma Public Utilities


Washington Public Power Supply System unfinished unit 5 (1978) near Satsop, WA, 2000
Courtesy Grays Harbor Community Development Corp.


 
Home About Us Fun & Travel Education Contact Us Sponsors Advanced Search

HistoryLink.org is the first online encyclopedia of local and state history created expressly for the Internet. (SM)
HistoryLink.org is a free public and educational resource produced by History Ink, a 501 (c) (3) tax-exempt corporation.